Not exactly. The use of the alternative means (field-fabricated bonding grid) to establish the equipotential bonding grid to extend under the deck constructed by paved walking surfaces as established in 680.26(c)(3), is only required when the deck is not constructed with poured concrete, wire mesh, and unencapsulated reinforcing steel.